CRC submits comments on the Glen Rd Hydro Revised Study Plan
Comments to FERC regarding Green Mountain Power's revised study plan in the relicensing process for the Glen Hydro Facility on the Mascoma River.
Comments to FERC regarding Green Mountain Power's revised study plan in the relicensing process for the Glen Hydro Facility on the Mascoma River.
September 1, 2021 Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Room 1A Washington, DC 20426 Re: Comments on
August 2022: Hydropower Updates Contents: FirstLight Power updates Great River Hydro updates What you can do! Need a refresh about why you are getting
April 2022: Hydropower Updates This month’s email is long – but we promise you’ll want to read to the end! Quick Glance We’ve
March 22, 2022 Low Impact Hydro Institute 329 Massachusetts Ave Suite 6 Lexington, MA 02420 Via email to: comments@lowimpacthydro.org Re: Comments on the 15 Mile
Connecticut River Hydropower Agreements Fail the Public’s River CRC opposes major elements of agreements addressing river flow and fish migration below Turners Falls dam Greenfield,
December 6, 2021 Shannon Ames, Executive Director Low Impact Hydro Institute 1167 Massachusetts Avenue Office 407 Arlington, MA 02476 Submitted electronically to: comments@lowimpacthydro.org
$130 million dollars is a big number. Until it isn’t. FirstLight Power, the owner of hydropower facilities in MA and CT, is seeking new federal
August 19, 2021 Shannon Ames, Executive Director Low Impact Hydropower Institute 1167 Massachusetts Avenue, Office 407 Arlington, MA 02476 Re: LIHI Project #19
August 5, 2021 Low Impact Hydropower Institute 1167 Massachusetts Avenue, Office 407, Arlington, MA 02476 Re: LIHI Project #80 – Gardner Falls Hydroelectric